Monday, March 16, 2009

Gantt Charts


Gantt Charts

Planning and Scheduling Complex Projects

Gantt Charts are important tools that help you plan and manage complex projects.

They help you work out the order in which tasks need to be carried out; allow you to identify the resources needed to complete the project, along with the times when these resources will be needed; help you work out the quickest possible time in which a project can be completed; and help you identify the "critical path" for a project. This is the sequence of tasks that must be completed on time if you are to complete the project by a particular date.

When a project is under way, Gantt Charts help you to monitor whether the project is on schedule. If it is not, they help you to pinpoint the remedial action necessary to put it back

on schedule.

These are all essential activities if you are going to manage projects successfully.

Sequential and parallel activities:

An essential concept behind project planning (and Critical Path Analysis as well) is that some activities are dependent on other activities being completed first. As a shallow example, it is not a good idea to start building a bridge before you have designed it!

These dependent activities need to be completed in a sequence, with each stage being more-or-less completed before the next activity can begin. We can call dependent activities 's

equential' or 'linear'.

Other activities are not dependent on completion of any other tasks. The

se may be done at any time before or after a particular stage is reached. These are nondependent or 'parallel' tasks.

How to Use the Tool:

To plan a project using a Gantt Chart, follow these steps:

1. List all activities in the plan
The first step is to list all of the tasks that need to be completed to deliv

er the project. For each task, show the earliest start date, estimated length of time it will take, and whether it is parallel or sequential. And if tasks are sequential, show which previous stage or stages they depend on.

You will end up with a task list like the one in figure 1. This example shows the task list for an example custom-written computer project. We will use this same example for both this section and the section on Critical Path Analysis and PERT. This will allow you to compare the results o

f the two approaches.

Figure 1. Gantt Chart Example: Planning a custom-written computer project
NB: The start week shows when resources become available. Whether a task is parallel or sequential depends largely on context.

Task

possible start

Length

Type

Dependent on...

1. High level analysis

week 1

5 days

sequential


2. Selection of hardware platform

week 1

1 day

sequential

1

3. Installation and commissioning of hardware

week 3

2 weeks

parallel

2

4. Detailed analysis of core modules

week 1

2 weeks

sequential

1

5. Detailed analysis of supporting utilities

week 1

2 weeks

sequential

4

6. Programming of core modules

week 4

3 weeks

sequential

4

7. Programming of supporting modules

week 4

3 weeks

sequential

5

8. Quality assurance of core modules

week 5

1 week

sequential

6

9. Quality assurance of supporting modules

week 5

1 week

sequential

7

10.Core module training

week 7

1 day

parallel

6

11.Development of accounting reporting

week 6

1 week

parallel

5

12.Development of management reporting

week 6

1 week

parallel

5

13.Development of management analysis

week 6

2 weeks

sequential

5

14.Detailed training

week 7

1 week

sequential

1-13

15.Documentation

week 4

2 weeks

parallel

13

2. Head up graph paper with the days or weeks through to task completion

3. Plot the tasks onto the graph paper

Next draw up a rough draft of the Gantt Chart. Plot each task on the graph paper, showing it

starting on the earliest possible date. Draw it as a bar, with the length of the bar being the length of the task. Above the task bars, mark the time taken to complete them. Do not worry about task scheduling yet: All you are doing is setting up the first draft of the analysis.

This will produce an untidy diagram like the one below:


4. Schedule Activities

Now take the draft Gantt Chart, and use it to schedule actions. Schedule them in such a way that sequential actions are carried out in the required sequence. Ensure that dependent activities do not start until the activities they depend on have been completed.

Where possible, schedule parallel tasks so that they do not interfere with sequential actions on the critical path. While scheduling, ensure that you make best use of the

resources you have available, and do not over-commit resource. Also allow some slack time in the schedule for holdups, overruns, quality rejections, failures in delivery, and so on.

A redrawn and scheduled version of the example project is shown below:


By drawing this Gantt Chart, you can see that:

  • If all goes well, the project can be completed in 10 weeks.
  • If you want to complete the task as rapidly as possible, you need:
    • 1 analyst for the first 5 weeks.
    • 1 programmer for 6 weeks starting week 4.
    • 1 programmer for 3 weeks starting week 6.
    • Quality assurance resource for weeks 7 and 9.
    • Hardware to be installed by the end of week 7.
  • Analysis, development and installation of supporting modules are essential activities that must be completed on time.
  • Hardware installation is a low priority task as long as it is completed by the end of week 7.

While this section describes how to draw a Gantt Chart manually, in practice project managers tend to use software tools like Microsoft Project to create Gantt Charts.

Not only do these ease the drawing of Gantt Charts, they also make modification of plans easier and provide facilities for monitoring progress against plans.

Key points:

Gantt charts are useful tools for planning and scheduling projects. They help you to assess how long a project will take to complete, determine the resources needed, and lay out the order in which tasks need to be carried out. They are useful in managing the dependencies between tasks.

When a project is under way, Gantt charts are useful for monitoring its progress. You can immediately see what should have been achieved at a particular point in time, and can therefore take remedial action to bring the project back on course if needed. This can be essential for the successful and profitable implementation of the project.

Most Project Managers use tools such as Microsoft Project to build and manage Gantt Charts.

No comments: